Value of project
$25M - $50M

Tender

Sep 2018

Construction
Start

Nov 2018

Construction
End

Apr 2020

The existing Gordon Road WWTP is expected to reach capacity of 12 ML/d in 2016. It will be necessary to upgrade treatment (Oxidation Ditch process) and infiltration capacity to 16ML/day, with allowance to receive sludge from Halls Head & Caddadup WWTPs.

WA 6210

Government agency - Water Corporation

Project Funding source - Western Australian Government

  • Major industry:

    Electric, gas, water & waste services

  • Major procurement method:

    To Be Determined

  • Next key date:

  • Project contracts:

    None available

For more information contact: Brian Robertson
629 Newcastle Street
Leederville WA 6007

Disclaimer: The Commonwealth of Australia (acting through the Department of Infrastructure and Regional Development) makes this material available on the understanding that users exercise their own skill and care with respect to its use. Read more