Value of project
$500M - $1B

Tender

Q2 (Apr-Jun)
2017

Construction
Start

Q2 (Apr-Jun)
2018

Construction
End

Q2 (Apr-Jun)
2021

Construct bridge/s and approaches.

The Haughton River Bridge project will see construction of a higher level bridge and road approaches to improve flood immunity at the Haughton River. Safety will be further enhanced with the elimination of two at grade rail crossings at the Bruce Highway intersections with Woodstock Giru Road and Hodel Road, south of Haughton.

This proposed project will improve flood immunity, safety and network efficiency on this section of the Bruce Highway.

Qld 4810

Government agency - Department of Transport and Main Roads

Project Funding source - Australian Government
Queensland Government

For more information contact: District Director (Northern)
44 Flinders Street
Townsville Qld 4810

Disclaimer: The Commonwealth of Australia (acting through the Department of Infrastructure and Regional Development) makes this material available on the understanding that users exercise their own skill and care with respect to its use. Read more