Potential for
Private investment

Value of project
$25M - $50M

Tender

Q1 (Jan-Mar)
2017

Construction
Start

Q3 (Jul-Sep)
2017

Construction
End

Q2 (Apr-Jun)
2019

The Scottsdale Irrigation Scheme (SIS) is designed to deliver 8,600 ML of high-reliability summer irrigation water to the areas of Scottsdale, Springfield, Bridport and Waterhouse. Surplus winter flows would be stored in the proposed Camden Rivulet Dam and distributed by a 73km network of underground pipelines and three local waterways: the Great Forester and Brid Rivers and Hurst Creek. The scheme will generate electricity through a mini-hydro power station at South Springfield.

TAS 7260

Government agency - Tasmanian Irrigation

Project Funding source - Tasmanian Government
Australian Government

  • Major industry:

    Electric, gas, water & waste services

  • Major procurement method:

    To Be Determined

  • Next key date:

  • Project contracts:

    None available

For more information contact: Luke Curtain